Obtaining a building permit is an essential part of starting construction work in Romania.
This legal document ensures the project complies with the applicable planning and construction regulations. Here are the main steps involved in obtaining a building permit:
1. Obtaining the planning certificate (CU)
The first step is to request the planning certificate from the municipality where the site is located. This document provides information about the site's legal, economic and technical status and sets out the conditions for the development. To obtain the CU, you will need:
- Completed application form
- Land ownership documents
- Cadastral plans
- Proof of payment of the applicable fee
2. Preparing the technical documentation for the building permit (D.T.A.C.)
The D.T.A.C. is prepared on the basis of the information in the planning certificate and includes:
- Architectural design
- Structural design
- Building services design (electrical, plumbing and heating)
These designs must be prepared by authorised specialists and approved in accordance with the applicable legislation.
3. Obtaining the required approvals and consents
Depending on the nature of the project and the requirements of the planning certificate, approvals and consents from various institutions may be required, such as:
- Environmental approval
- Approval from the Inspectorate for Emergency Situations
- Approvals from utility providers (water, sewerage, electricity and gas)
4. Submitting documentation and obtaining the building permit
After completing the D.T.A.C. and obtaining the required approvals, the full application is submitted to the municipality. Documentation must include:
- Application for the building permit
- Planning certificate
- D.T.A.C.
- Approvals and consents obtained
- Proof of payment of the permit fee
Under the legislation, the issuing authority is required to issue the building permit within 30 days of the submission of complete and correct documentation.
5. Do you also provide interior design services?
Yes. We provide fully bespoke interior design, tailored to your preferences and needs, using innovative solutions and quality materials.
5. Starting construction work
Once the building permit is obtained, work can begin, subject to the conditions and terms set out in the document. It is important to notify the municipality and the State Inspectorate for Construction of the start of works.
Conclusion
Following these steps supports the legality and compliance of your project with the applicable standards. Observing the procedures and collaborating with authorised professionals are essential to the success of any construction investment.